| Time frame for Implementation
The times described below are used as a general reference. Timelines depend on the size of the job and location.
- Initial engineering design period: 2 weeks (excluding customer approvals).
- Initial production period: 2 weeks (production of approximately 20 towers).
- Sea freight from USA to Middle East/Asia: 17-26 days.
- Typical foundation construction: 10-14 days (pier and pad in normal soil)
- Typical tower erection period: 5 days (40 meter tower, 3 legged tubular construction)
The RPI Integrated Tower Solution is based on the formation of a partnership between the customer and Rohn Products International. It allows for the unexpected and keeps the customer focused on his core business. RPI handles the task of tower construction. We invite you to contact us at any time by phone, fax, email or personal visit to find out how we can identify the added value we can bring to your project.
|
|
|